Skip to main content

Dry Gas Seal Failure Modes

BY BHUSHAN NIKAM.

Invented in the mid-20th century and typically equipped in process gas centrifugal, dry gas screw compressors and expanders, dry gas seals (DGS) are the preferred gas lubricated dry seal solutions available on the market. They have become the standard for new machines.


DGS are robust, simple, consume less power, and are more efficient in reducing leakage than their predecessor. Various configurations such as tandem with and without an intermediate labyrinth (Figure 1), single (Figure 2), and double (Figure 3) are available & shall be selected based on process requirements. In this article, we discuss the various DGS failure modes and how they should be addressed: 


PRESSURIZED HOLD/STANDBY

Pressurized hold, also called settle-out condition, occurs when the compressor remains at a standstill, but the casing is pressurized. If an alternate process gas lacks sufficient pressure and flow, process gas enters the seal cavity through the process labyrinth and contaminates the primary seal. This causes seal damage when the compressor is restarted. Minimum ambient site temperature also must be considered as the seal will be at the same temperature during standstill conditions, which will cause the process gas to condense and deposit on seal face grooves.

To avoid this kind of failure, the seal gas must be supplied with the required pressure even during a blackout. An alternate supply of seal gas should be considered when gas is not available from the compressor discharge. But it should not change the composition of the process gas. A seal gas booster should be considered when alternate gas is unavailable.

START-UP OR COMMISSIONING

The cause of the majority of DGS failures is contamination. This happens mostly during commissioning by not following OEM recommendations and best practices. Seal gas panel components including piping are properly cleaned and flushed with air, and end connections are blinded and dispatched to the site. However, site situations are always different. The piping upstream of the console must also be cleaned thoroughly including interconnecting piping between the console and the compressor. Corrosion inhibitors must be removed. The seal gas supply temperature dew point margin must be higher than or equal to the recommended value as per API. Failure to do any of the above will lead to contamination followed by degradation of the lift-off effect, friction between the static and rotating faces, parts deformation, O-ring extrusion, heat generation causing thermal shock on the rotating seat, and eventually failure of the rotating and or static rings.

NORMAL OPERATION

Although a DGS is less susceptible to failure during continuous normal operation, it may happen due to upset conditions leading to contaminated seal gas supply or condensate formation as a result of pressure drop across conditioning equipment. The flow velocity requirement across the process labyrinth varies depending on the process gas, usually 5 m/s. High velocity must be considered for some processes. If available pressure is not enough, consider installing a seal gas booster which will keep pressure at the seal cavity higher than on the process side. Ensure that a properly sized coalescing seal gas filter is installed which will filter out particles above 3μm. The gap between rotating faces is 3-5μm (a human hair is 70μm). Additional requirements, as per the recent API 692 code, should be considered as necessary.

SEPARATION SEAL FAILURE

A separation seal, also known as a barrier or tertiary seal, is located in between the DGS and the bearing box. Its purpose is to avoid lube oil ingress from the bearing to DGS side during normal operation and minimize process gas flow to the bearing side in the event of DGS failure. Flow consumption is much less than the secondary side. But depending on the type of seal applied, enough flow is necessary to avoid oil ingress to the DGS side. Nitrogen is typically used but dry air can also be supplied if the process allows it and does not create an explosive mixture. On the other side, high flow is not desirable as it may over-pressurize the lube oil reservoir. The vent line must be checked regularly and any oil traces should be drained and rectified.

REVERSE PRESSURIZATION

Reverse pressure occurs when downstream pressure is higher than the upstream supply pressure. If specified, a seal should be designed for reverse differential pressure as recommended by API. This must be confirmed by the DGS vendor as well. During reverse pressurization, contaminated gas or liquid droplets can travel from the flare vent line back to seal faces resulting in O-ring dislodging, loss of performance, and subsequent risk of seal damage. A differential pressure control valve with PDIT can be applied to avoid these issues. If not, necessary arrangements should be implemented so as not to reverse pressurize the DGS. Confirm flare line minimum, normal, and maximum pressure with the customer. Ensure DGS leakage gas does not create an explosive mixture with other hazardous gases in the flare.

RAPID DEPRESSURIZATION

The compressor casing may be depressurized after shutdown in case of over-haul, emergency shutdown, planned maintenance, or as per process requirements. DGS O-ring material must be chosen based on the depressurization rate. Consult with seal vendors if the decompression rate is different a standard application. If special considerations aren’t given to the selection of O-rings, they can be subject to explosive decompression due to rapid depressurization. Additionally, the decompression rate must be selected right at the basic design stage. Special attention must be given to avoid the Joule Thompson effect based on gas composition. This can lead to condensation of the gas and the process side may be exposed to Minimum Design Metal Temperature (MDMT). If material is not selected according to MDMT, the subject material may fail.

CONDENSATE OR LIQUID FORMATION

Gases and air have dew points which vary based on pressure, temperature, and type of gas (Figure 4). The gas used as a seal gas from the compressor discharge undergoes reduction in pressure and temperature which causes condensation. Similarly, when the dew point temperature is achieved, condensate forms. Eventually, droplets travel through the rotating and stationary seal faces where they will create a blistering effect resulting in failure of the seals faces.

The solution is to follow the rule of chemistry and perform a dew point analysis. The designer should check gas properties from the compressor datasheet and reconfirm these with the client as smaller changes in composition can affect the dew point. Plot the dew point line for possible cases, calculate the dew point, and check its margin from the supplied temperature. The delta T should be equal to or higher than that recommended in API. If the margin is less, gas conditioning will be necessary to keep the gas dry as it passes through the seal gas system. Only the most likely failure scenarios are addressed here. But DGS failure can be caused by various factors depending on the site situation.

■ Bhushan Nikam is a Project Engineer for a major turbomachinery equipment manufacturing organization. He holds a bachelor’s degree in Mechanical Engineering from the University of Pune, IN. He can be reached at nikambb007@gmail.com.

Source:  Turbomachinery Magazine

Comments

Popular posts from this blog

John Crane's Type 28 Dry Gas Seals: How Does It Work?

How Does It Work? Highest Pressure Non-Contacting, Dry-Running Gas Seal Type 28 compressor dry-running gas seals have been the industry standard since the early 1980s for gas-handling turbomachinery. Supported by John Crane's patented design features, these seals are non-contacting in operation. During dynamic operation, the mating ring/seat and primary ring/face maintain a sealing gap of approximately 0.0002 in./5 microns, thereby eliminating wear. These seals eliminate seal oil contamination and reduce maintenance costs and downtime. John Crane's highly engineered Type 28 series gas seals incorporate patented spiral-groove technology, which provides the most efficient method for lifting and maintaining separation of seal faces during dynamic operation. Grooves on one side of the seal face direct gas inward toward a non-grooved portion of the face. The gas flowing across the face generates a pressure that maintains a minute gap between the faces, optimizing flui...

Pump Shaft Breakage: Case Studies and Solutions

By NTS Pump shaft breakage is a common issue that can cause costly downtime and repairs in various industries. In this article, we will explore several case studies of pump shaft breakage and the solutions implemented to prevent future failures. Case Study 1: Chemical Processing Plant A chemical processing plant experienced repeated pump shaft breakages in their cooling water pumps. Investigation revealed that the pumps were not properly aligned with the motor and had excessive vibration due to the misalignment. This caused the pump shaft to fatigue and break over time. The problem was resolved by realigning the pumps and installing vibration monitoring equipment to detect any future misalignment or excessive vibration. Case Study 2: Wastewater Treatment Plant A wastewater treatment plant had issues with pump shaft breakage in their sludge pumps. The pumps were designed with a straight shaft and lacked a flexible coupling, causing excessive stress and vibration on the pump sha...

Benefits of Remanufacturing bearings

Replacing bearings can prove to be expensive, both in new bearing cost and lost productivity. Some manufacturer takes bearings and expertly remanufactures them to like-new condition for extended service.

What does The term ‘maintenance’ mean ?

The term ‘maintenance’ means to keep the equipment in operational condition or repair it to its operational mode. Main objective of the maintenance is to have increased availability of production systems, with increased safety and optimized cost.

How To Troubleshoot the Effective Maintenance

Knowledge of effective troubleshooting practices can go a long way toward getting equipment back on line quickly. Unfortunately, due to many reasons troubleshooting occupies too much of a technician's time. You might consider these six key elements to improve your troubleshooting skills: Understand the system Understand the problem and history Eliminate the obvious Develop possible causes and theories Eliminate causes, start with what is easy, or likely Validate and document the solution Firstly, if you do not understand the system and how it functions, you will be thrashing around in the dark. I found the best time to understand was while the equipment was running and producing product. Time spent studying the process while the equipment was running paid huge benefits when issues arose. It was always beneficial to listen closely to what the operator saw, heard, noticed, and did, just before the problem occurred. I learned quickly that a good operator was a great asset. ...